The construction work at the Japan Road School is progressing well. Below is a list of things have been completed during the last month.
1. Clearance of the area for the building has been completed. Stumps have been removed.
2. Construction of temporary store is complete except for the fixing of door & windows.
3. Drilling of borehole for water has been completed. Fixing of an uplift electric motor is pending.
4. Major excavation works for the building and water reservoir have been completed.
5. Setting of excavated foundations is underway.
QWT Photos
Categories
Recent Posts
Archives
- April 2020
- May 2019
- March 2019
- July 2018
- April 2018
- May 2017
- February 2017
- June 2016
- May 2016
- November 2015
- October 2015
- July 2015
- June 2015
- May 2015
- March 2015
- October 2014
- August 2014
- July 2014
- June 2014
- April 2014
- March 2014
- February 2014
- November 2013
- July 2013
- April 2013
- January 2013
- December 2012
- October 2012
- July 2012
- June 2012
- May 2012
- April 2012
- March 2012
- February 2012
- December 2011
- August 2011
Recent Comments